We spent 2 hours this morning with the construction manager for the pre-drywall inspection. I pointed out some things that need attention we asked a bunch of questions and he was real thorough. As you’ll see insulation is just about done. On Tuesday they are going to start drywall and the following Thursday they are going to pour in the Gyp-Crete on our main floor. He’s expecing about a week to get the drywall up then the siding will be hung.
The pics are going to be backwards this week, we started in the master bath and worked our way down.
Master Bath


Master Bedroom


Attic access in master bedroom walk-in closet.

When the drywall is done they will come in and spray in the attic insulation, 12-14″ worth of the stuff. The piece of drywall they use to fill the access hole will have a sheet of the standard insulation glued to the back of it. The attic is not meant for storage, but he went on to say to use your best judgement if you really must store stuff like empty boxes or luggage up there.

Hall bath.

Upstairs hallway. The steel box is for the smoke detectors, the blue is the hall light.

Left bedroom ceiling.

I took this picture to illustrate the 1″ gap that is to accomodate the Gyp-Crete that is going to be poured onto the entire floor of the main level.

The 100mm carpet pad will go on top of the Gyp-Crete, then the carpet. In the kitchen and family room a rubber mat will go down on the Gyp-Crete then the tile will go on top of that.
Once the drywall is all hung they bring in an acoustic engineer who does sound testing throughout each unit. He uses sound emitting and recording equipment to test decibal levels both to hear sound coming from other units and to hear sound coming out of the unit. The construction manager explained all the testing equipment that is brought in, it was pretty impressive. If a unit fails the tests they have to rip out the drywall and re-do all the insulation and sound dampening materials.
Shared wall in living room.

Opposite shared wall.

Living/Dining room, Kitchen on other side of wall.

Kitchen ceiling. There wasn’t supposed to be insulation in the ceiling on our main floor but the trades put it in accidently. Oops. It’s not going to be pulled back out unless they need it to finish another unit.

Another of the extra insulation. The blue cable is my data lines.

Corner of the family room, powder room and furnace closet are on the other side. That return is one of two in the house, I will have filters at each. The other is at the top of the stairs on the level above…which is going to make filter changes very interesting.

Another of the kitchen. There are 5 recessed lights total, the 1 light above the sink is on it’s own switch.

This is the spray-in insulation in the ceiling of our front porch. This should all be closed in and close to done by the end of next week.

This is the back wall of the garage.

The steel furring strips are how what they use to attach the drywall. By screwing the drywall into these strips the noise from the walls is not transferred into the studs where it would vibrate through the structure. Also, they hang the walls first, then put the ceilings in. This is another step to help reduce vibration from above. essentially the drywall is hanging off of the structure of the house. Pretty neat stuff.
Garage ceiling.

Outlet for the garage door opener and the light fixture.

I took a few more pics of the ceiling in the garage because something the construction manager pointed out was to make sure that whoever installs the garage opener doesn’t follow the screw holes from the drywall to mount the motor because the screws follow the furring strips and not the studs. With the pictures I shouldn’t have a problem showing the studs for whoever installs it.
We’re still on schedule for a December delivery and the crew is pretty happy with themselves because they’ve been doing real well with the county inspections which is great. That’s it for now.